The duration of the works is 24 months, of which six months will be allocated to the design. The warranty for the work is 48 months.

According to the contract, the motorway sector spans 6.3 km, plus 3.7 km of national road to 4 lanes, with a median separator.

Râşnov - Cristian sector is part of Lot 2 (the Comarnic - Braşov section), an integral part of the Bucharest - Braşov highway, which has a total length of 168 km.

The Comarnic - Brasov motorway section is divided into 5 sectors. Sectors 1 and 5 are those from Comarnic, namely from Brasov, with a total length of approximately 10 kilometers, to which are added connecting roads.

The total length of the Comarnic - Braşov highway sector is 58 km and the estimated value for this intervention is 997 million euros without VAT, or 1.237 billion euros VAT. (source: AGERPRES)